[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910947":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910947,587,2,"多选题","（2019年考题）下列工程项目目标控制方法中,可用来控制工程造价和工程进度的方法有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","香蕉曲线法",true,{"key":16,"text":17,"correct":18},"B","目标管理法",false,{"key":20,"text":21,"correct":14},"C","S曲线法",{"key":23,"text":24,"correct":18},"D","责任矩阵法",{"key":26,"text":27,"correct":18},"E","因果分析图法","AC","S曲线可用于控制工程造价和工程进度,与S曲线法相同,香蕉曲线同样可用来控制工程造价和工程进度。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]