[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910940":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910940,587,2,"多选题","（2020年真题）在工程建设实施过程中，为了做好环境保护全体工程与环保措施工程必须同时进行的工作有（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标",false,{"key":16,"text":17,"correct":18},"B","设计",true,{"key":20,"text":21,"correct":18},"C","施工",{"key":23,"text":24,"correct":14},"D","竣工结算",{"key":26,"text":27,"correct":18},"E","投入运行","BCE","P69-74 在项目实施阶段，必须做到'三同时'，即主体工程与环保措施工程同时设计、同时施工、同时投入运行",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]