[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910893":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910893,587,2,"多选题","依据项目结构分解方法不同，常见的资金使用计划的编制方法有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按工程造价构成编制资金使用计划",true,{"key":16,"text":17,"correct":14},"B","按工程项目组成编制资金使用计划",{"key":19,"text":20,"correct":21},"C","按工程施工周期编制资金使用计划",false,{"key":23,"text":24,"correct":14},"D","按工程进度编制资金使用计划",{"key":26,"text":27,"correct":21},"E","按工程费用估算编制资金使用计划","ABD","依据项目结构分解方法不同，资金使用计划的编制方法也有所不同，常见的有按工程造价构成编制资金使用计划，按工程项目组成编制资金使用计划和按工程进度编制资金使用计划。这三种不同的编制方法可以有效地结合起来，组成一个详细完备的资金使用计划体系。2020教材P339-341",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]