[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910887":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910887,587,2,"多选题","企业对项目经理部可控责任成本的考核包括（ ），",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","A：项目成本目标和阶段成本目标完成情况",true,{"key":16,"text":17,"correct":14},"B","B：建立以项目经理为核心的成本管理责任制的落实情况",{"key":19,"text":20,"correct":14},"C","C：成本计划的编制和落实情况",{"key":22,"text":23,"correct":14},"D","D：在成本管理中贯彻责权利结合原则的执行情况",{"key":25,"text":26,"correct":27},"E","E：对各分包工程的检查情况",false,"ABCD","2020版教材P351 本题考查的是成本考核。企业对项目经理部可控责任成本的考核包括：①项目成本目标和阶段目标完成情况；②建立以项目经理为核心的成本管理责任制的落实情况；③成本计划的编制和落实情况；④对各部门、各施工队伍和班组责任成本的检查和考核情况；⑤在成本管理中贯彻责权利结合原则的执行情况。除此之外，为层层落实项目成本管理工作，项目经理对所属部门、各施工队和班组也要进行成本考核，主要考核其责任成本的完成情况。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]