[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910879":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910879,587,2,"多选题","工程项目施工过程中的综合成本分析包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A：检验批施工成本分析",false,{"key":16,"text":17,"correct":18},"B","B：分部分项工程成本分析",true,{"key":20,"text":21,"correct":14},"C","C：单位工程施工成本分析",{"key":23,"text":24,"correct":18},"D","D：月（季）度施工成本分析",{"key":26,"text":27,"correct":14},"E","E：建设项目决算成本分析","BD","2020版教材P350 综合成本的分析方法。所谓综合成本，是指涉及多种生产要素，并受多种因素影响的成本费用，综合成本的分析方法包括分部分项工程成本、月（季）度成本、年度成本等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]