[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910872":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910872,587,2,"多选题","施工合同签订后，工程项目施工成本计划的常用编制方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","A：专家意见法",false,{"key":16,"text":17,"correct":14},"B","B：功能指数法",{"key":19,"text":20,"correct":21},"C","C：目标利润法",true,{"key":23,"text":24,"correct":21},"D","D：技术进步法",{"key":26,"text":27,"correct":21},"E","E：定率估算法","CDE","2020版教材P343 本题考查的是施工成本管理。成本计划的编制方法主要有： ①目标利润法； ②技术进步法； ③按实计算法； ④定率估算法（历史资料法）。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]