[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910867":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910867,587,2,"多选题","从工地管理角度看，分标时应考虑的因素是指( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程量的大小",false,{"key":16,"text":17,"correct":14},"B","劳动力、材料、设备的调配",{"key":19,"text":20,"correct":21},"C","工程进度的衔接",true,{"key":23,"text":24,"correct":14},"D","建设资金、设计图纸供应",{"key":26,"text":27,"correct":21},"E","工地现场的布置和干扰","CE","2020版教材P315 从工地管理角度看，分标时应考虑两方面问题：一是工程进度的衔接，二是工地现场的布置和干扰。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]