[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910860":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910860,587,2,"多选题","下列工程项目中，不宜采用固定总价合同的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A：建设规模大且技术复杂的工程项目",true,{"key":16,"text":17,"correct":18},"B","B：施工图纸和工程量清单详细而明确的项目",false,{"key":20,"text":21,"correct":14},"C","C：施工中有较大部分采用新技术，且施工单位缺乏经验的项目",{"key":23,"text":24,"correct":14},"D","D：施工工期紧的紧急工程项目",{"key":26,"text":27,"correct":14},"E","E：承包风险较大，各项费用不易准确估算的项目","ACDE","2020版教材P316 选项AE，建设规模大且技术复杂的工程项目，承包风险较大，各项费用不易准确估算，因而不宜采用固定总价合同。选项C，施工中有较大部分采用新技术，且施工单位缺乏经验的项目，不宜采用固定总价合同。选项B，如果已完成工程项目的施工图设计、施工图纸和工程量清单详细而明确，则可选择总价合同。选项D，施工工期紧的紧急工程项目应选择成本加酬金合同较为合适。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]