[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910858":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910858,587,2,"多选题","根据《标准施工招标文件》的相关规定，在履行合同过程中发生争议，采用争议评审方式的，发包人和承包人应在（ ），协商成立争议评审组。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A：开工日后的28天内",true,{"key":16,"text":17,"correct":18},"B","B：订立施工合同后",false,{"key":20,"text":21,"correct":18},"C","C：开工之日",{"key":23,"text":24,"correct":18},"D","D：施工合同生效后",{"key":26,"text":27,"correct":14},"E","E：争议发生后","AE","2020版教材P323 本题考查的是施工合同示范文本。采用争议评审的，发包人和承包人应在开工日后28天内或在争议发生后，协商成立争议评审组。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]