[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910856":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910856,587,2,"多选题","根据《标准施工招标文件》，下列因不可抗力导致的后果中，由发包人承担责任的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A：已运至施工场地的材料的损害",true,{"key":16,"text":17,"correct":18},"B","B：承包人的停工损失",false,{"key":20,"text":21,"correct":14},"C","C：因工程损害造成的第三者财产损失",{"key":23,"text":24,"correct":14},"D","D：停工期间承包人应监理人要求照管工程的费用",{"key":26,"text":27,"correct":18},"E","E：承包人设备的损坏","ACD","2020版教材P322 不可抗力导致的人员伤亡、财产损失、费用增加和（或）工期延误等后果，由合同双方按以下原则承担：①永久工程，包括己运至施工场地的材料和工程设备的损害，以及因工程损害造成的第三者人员伤亡和财产损失由发包人承担；②承包人设备的损坏由承包人承担；③发包人和承包人各自承担其人员伤亡和其他财产损失及其相关费用；④承包人的停工损失由承包人承担，但停工期间应监理人要求照管工程和清理、修复工程的金额由发包人承担；⑤不能按期竣工的，应合理延长工期，承包人不需支付逾期竣工违约金。发包人要求赶工的，承包人应采取赶工措施，赶工费用由发包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]