[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910845":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910845,587,2,"多选题","根据FIDIC《土木工程施工合同条件》，工程师在工程付款控制方面的权力主要表现在（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","A：批准使用暂定金额和计日工",true,{"key":16,"text":17,"correct":14},"B","B：签发各种付款证书",{"key":19,"text":20,"correct":14},"C","C：确定变更工程的估价",{"key":22,"text":23,"correct":24},"D","D：承包商修改施工进度计划",false,{"key":26,"text":27,"correct":24},"E","E：审核承包商的索赔","ABC","2020版教材P328 工程付款控制。主要表现在：确定变更工程的估价；批准使用暂定金额和计日工；签发各种付款证书等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]