[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910842":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910842,587,2,"多选题","在工程项目限额设计实施程序中，目标推进通常包括（ ）两个阶段。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制定限额设计的质量目标",false,{"key":16,"text":17,"correct":18},"B","限额初步设计",true,{"key":20,"text":21,"correct":14},"C","制定限额设计的造价目标",{"key":23,"text":24,"correct":18},"D","限额施工图设计",{"key":26,"text":27,"correct":14},"E","制定限额设计的进度目标","BD","2020版教材P306 本题考查的是限额设计。目标推进通常包括限额初步设计和限额施工图设计两个阶段。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]