[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910829":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910829,587,2,"多选题","工程项目多方案比选主要包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工艺方案比选",true,{"key":16,"text":17,"correct":14},"B","规模方案比选",{"key":19,"text":20,"correct":14},"C","选址方案比选",{"key":22,"text":23,"correct":14},"D","污染防治措施方案比选",{"key":25,"text":26,"correct":27},"E","工程实施方案比选",false,"ABCD","2020版教材P287 本题考查的是多方案比选。工程项目多方案比选主要包括：工艺方案比选、规模方案比选、考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com 选址方案比选，甚至包括污染防治措施方案比选等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]