[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910808":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910808,587,2,"多选题","工程项目限额设计的实施程序包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","目标实现",false,{"key":16,"text":17,"correct":18},"B","目标制定",true,{"key":20,"text":21,"correct":18},"C","目标分解",{"key":23,"text":24,"correct":18},"D","目标推进",{"key":26,"text":27,"correct":18},"E","成果评价","BCDE","2020版教材P306 本题考查的是限额设计。限额设计的实施是建设工程造价目标的动态反馈和管理过程，可分为目标制定、目标分解、目标推进和成果评价四个阶段。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]