[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910807":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910807,587,2,"多选题","估算项目的经营成本时，应在总成本费用中扣除（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工资及福利费",false,{"key":16,"text":17,"correct":18},"B","折旧费",true,{"key":20,"text":21,"correct":14},"C","燃料和动力费",{"key":23,"text":24,"correct":18},"D","摊销费",{"key":26,"text":27,"correct":18},"E","财务费用","BDE","2020版教材P305 本题考查的是工程项目经济评价报表的编制。估算项目的经营成本时，应在总成本费用中扣除折旧费、摊销费、财务费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]