[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910739":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910739,587,2,"多选题","造成价值工程活动对象的价值系数V小于1的可能原因有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","评价对象的显示成本偏低",false,{"key":16,"text":17,"correct":18},"B","功能现实成本大于功能评价值",true,{"key":20,"text":21,"correct":14},"C","可能存在着不足的功能",{"key":23,"text":24,"correct":18},"D","实现功能的条件或方法不佳",{"key":26,"text":27,"correct":18},"E","可能存在着过剩的功能","BDE","V＜1，即功能现实成本大于功能评价值。表明评价对象的现实成本偏高，而功能要求不高。这时，一种可能是由于存在着过剩的功能，另一种可能是功能虽无过剩，但实现功能的条件或方法不佳，以致使实现功能的成本大于功能的现实需要。这两种情况都应列入功能改进的范围，并且以剔除过剩功能及降低现实成本为改进方向，使成本与功能比例趋于合理。2020教材P204-219",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]