[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910730":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910730,587,2,"多选题","下列关于价值工程的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","价值工程的核心是对产品进行功能分析",true,{"key":16,"text":17,"correct":18},"B","价值工程的应用重点是在产品生产阶段",false,{"key":20,"text":21,"correct":14},"C","价值工程将产品的价值、功能和成本作为一个整体考虑",{"key":23,"text":24,"correct":14},"D","价值工程需要将产品的功能定量化",{"key":26,"text":27,"correct":14},"E","价值工程可用来寻求产品价值的提高途径","ACDE","2020版教材P203 本题考查的是价值工程的基本原理和工作程序。价值工程的核心是对产品进行功能分析。价值工程将产品价值、功能和成本作为一个整体同时来考虑。价值工程要求特功能定量化，即将功能转化为能够与成本直接相比的量化值。价值工程可用来寻求产品价值的提高途径。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]