[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910719":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910719,587,2,"多选题","有三项投资，资料如下，要比较哪项投资有利，可以使用的方法是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","NPV法",false,{"key":16,"text":17,"correct":18},"B","NAV法",true,{"key":20,"text":21,"correct":18},"C","最小公倍数法",{"key":23,"text":24,"correct":14},"D","IRR法",{"key":26,"text":27,"correct":18},"E","△IRR法","BCE","题目考核的是不同计算期的互斥方案的评价方法。常用的动态评价方法有净年值（NAV）、最小公倍数（方案重复法）、研究期法、无限计算期法、增量投资内部收益率法（△IRR）；2020教材P185-195",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]