[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910671":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910671,587,2,"多选题","工程双代号网络计划中，关键工作是指（ ）的工作",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总时差最小",true,{"key":16,"text":17,"correct":18},"B","自由时差最小",false,{"key":20,"text":21,"correct":18},"C","时间间隔为零",{"key":23,"text":24,"correct":14},"D","最迟完成时间与最早完成时间的差值最小",{"key":26,"text":27,"correct":18},"E","两端为关键节点的工作","AD","2020版教材P126 本题考查的是双代号网络计划时间参数的计算方法。在网络计划中，总时差最小的工作为关键工作。特别地，当网络计划的计划工期等于计算工期时，总时差为零的工作就是关键工作。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]