[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910669":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910669,587,2,"多选题","在工程项目实施过程中，当实际进度偏差影响到后续工作、总工期而需要调整进度计划时，其调整方法主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增派施工人员",false,{"key":16,"text":17,"correct":18},"B","改变某些工作间的逻辑关系",true,{"key":20,"text":21,"correct":18},"C","缩短某些工作的持续时间",{"key":23,"text":24,"correct":14},"D","取消部分施工项目",{"key":26,"text":27,"correct":14},"E","提前进行后续施工","BC","2020版教材P140 本题考查的是网络计划执行中的控制。当实际进度偏差影响到后续工作、总工期而需要调整进度计划时，其调整方法主要有两种：①改变某些工作间的逻辑关系。②缩短某些工作的持续时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]