[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910667":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910667,587,2,"多选题","对工程网络计划进行优化，其目的是使该工程（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总成本最低",true,{"key":16,"text":17,"correct":18},"B","资源强度最低",false,{"key":20,"text":21,"correct":14},"C","资源需用量尽可能均衡",{"key":23,"text":24,"correct":18},"D","资源需用量最少",{"key":26,"text":27,"correct":14},"E","计算工期满足要求工期","ACE","2020版教材P134 本题考查的是网络计划的优化。网络计划的优化目标应按计划的需要和条件选定，包括工期优化，费用优化和资源优化。工期优化是指网络计划的计算工期不满足要求工期时，通过压缩关键工作持续时间以满足要求工期目标的过程。费用优化指寻求工程总成本最低时的工期安排。资源优化需要使资源需用量尽可能地均衡。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]