[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910665":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910665,587,2,"多选题","下列选项中，属于改变关键线路和超过计划工期的非关键线路上的有关工作之间的逻辑关系的措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","将顺序作业改为平行作业",true,{"key":16,"text":17,"correct":18},"B","提高劳动效率",false,{"key":20,"text":21,"correct":18},"C","增加资源投入",{"key":23,"text":24,"correct":18},"D","采用轮班工作制",{"key":26,"text":27,"correct":14},"E","搭接作业以及分段组织流水作业","AE","2020版教材P140 本题考查的是网络计划执行中的控制。当工程项目实施中产生的进度偏差影响到总工期，且有关工作的逻辑关系允许改变时，可以改变关键线路和超过计划工期的非关键线路上的有关工作之间的逻辑关系，达到缩短工期的目的。例如，将顺序进行的工作改为平行作业、搭接作业以及分段组织流水作业等，都可以有效地缩短工期。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]