[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910664":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910664,587,2,"多选题","某分部工程双代号时标网络计划执行到第6天和第10天结束时，检查其实际进度如下图前锋线所示，检查结果表明（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第6天结束检查时，工作B的实际进度不影响总工期",true,{"key":16,"text":17,"correct":18},"B","第6天结束检查时，工作D的总时差尚有2天",false,{"key":20,"text":21,"correct":14},"C","第10天结束检查时，工作E的实际进度会影响总工期",{"key":23,"text":24,"correct":14},"D","第10天结束检查时，工作C的实际进度影响工期1天",{"key":26,"text":27,"correct":14},"E","在第6天到第10天内，工作D的实际进度加快1天","ACDE","2020版教材P138 本题考查的是双代号时标网络计划。第6天结束检查时，工作D的总时差尚有1天。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]