[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910663":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910663,587,2,"多选题","在工程网络计划中，关键线路是指（ ）的线路。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","双代号网络计划中总持续时间最长",true,{"key":16,"text":17,"correct":14},"B","双代号时标网络计划中没有波形线",{"key":19,"text":20,"correct":21},"C","双代号网络计划中由关键节点组成",false,{"key":23,"text":24,"correct":14},"D","单代号网络计划中相邻工作时间间隔均为零",{"key":26,"text":27,"correct":21},"E","单代号网络计划中由关键工作组成","ABD","2020版教材P128 关键线路上的节点称为关键节点。关键节点必然处在关键线路上，但由关键节点组成的线路不一定是关键线路。在单代号网络计划中，利用关键工作确定关键线路，总时差最小的工作为关键工作，将这些关键工作相连，并保证相邻两项关键工作之间的时间间隔为零而构成的线路就是关键线路。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]