[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910661":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910661,587,2,"多选题","某工程网络计划图中，D工作的紧后工作为E和 F，其持续时间分别为6天、3天、2天，D工作第8天开始，E和F工作均于第18天必须最迟完成，则以下参数正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","D工作自由时差为1天",false,{"key":16,"text":17,"correct":18},"B","D工作自由时差为0天",true,{"key":20,"text":21,"correct":14},"C","E工作的总时差为0天",{"key":23,"text":24,"correct":14},"D","D工作的最迟开始时间为第10天",{"key":26,"text":27,"correct":18},"E","F工作总时差为2天","BE","2020版教材P130 该题网络图如下图所示： 由以上计算可知，选项BE正确。选项A的D工作自由时差应为0天，选项C中E工作的总时差应 为1天，选项D中最迟开始时间应为第9天。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]