[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910660":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910660,587,2,"多选题","工程网络计划中，关键工作是指（ ）的工作。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自由时差最小",false,{"key":16,"text":17,"correct":18},"B","总时差最小",true,{"key":20,"text":21,"correct":14},"C","时间间隔为零",{"key":23,"text":24,"correct":18},"D","最迟完成时间与最早完成时间的差值最小",{"key":26,"text":27,"correct":14},"E","开始节点和完成节点均为关键节点","BD","2020版教材P126 工程网络计划中，关键工作是指总时差最小的工作；总时差等于最迟完成时间与最早完成时间的差值。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]