[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910659":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910659,587,2,"多选题","某工程双代号网络计划如下图所示，图中已标由各节点的最早时间和最迟时间。该计划表明（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作1-2为关键工作",true,{"key":16,"text":17,"correct":14},"B","工作2-4的总时差为零",{"key":19,"text":20,"correct":21},"C","工作2-5的自由时差为1",false,{"key":23,"text":24,"correct":21},"D","工作3-4为非关键工作",{"key":26,"text":27,"correct":14},"E","工作5-6的总时差为1","ABE","2020版教材P127 采用标号法确定关键线路：①→②→④→⑥和①→③→④→⑥，所以选项A、B是正确选项；工作2-5的EF=II，工作5-6的ES=15，工作2-5的自由时差为4；工作3-4是关键线路上的工作，所以是关键工作；工作5-6的ES=15，计划工期为20，工作5-6的LF=20，工作5-6的LS=16，所以工作5-6的总时差为1。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]