[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910656":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910656,587,2,"多选题","某工程双代号网络计划如下图所示，图中已标出各个节点的最早时间和最迟时间。该计划表明（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作1-2的自由时差为2",false,{"key":16,"text":17,"correct":18},"B","工作2-5的总时差为7",true,{"key":20,"text":21,"correct":18},"C","工作3-4为关键工作",{"key":23,"text":24,"correct":14},"D","工作3-5为关键工作",{"key":26,"text":27,"correct":14},"E","工作4-6的总时差为零","BC","2020版教材P127 由图可知，工作1-2的最早完成时间=o+4=4， 工作2-5的最早开始时间=4，最迟开始时间=14-3=11，因此工作2-5的总时差=11-4=7，节点③④⑤⑥均为关键节点，对于工作35，由于6+5不等于14，因此工作3-5是非关键工作，工作3-4为关键工作，工作4-6的总时差=21-5-14=2。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]