[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910655":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910655,587,2,"多选题","根据优化目标的不同，网络计划的优化可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","控制措施优化",false,{"key":16,"text":17,"correct":18},"B","工期优化",true,{"key":20,"text":21,"correct":14},"C","管理线路优化",{"key":23,"text":24,"correct":18},"D","费用优化",{"key":26,"text":27,"correct":18},"E","资源优化","BDE","2020版教材P134 本题考查的是网络计划的优化。网络计划的优化目标应按计划任务的需要和条件选定，包括工期目标、费用目标和资源目标。根据优化目标的不同，网络计划的优化可分为工期优化、费用优化和资源优化三种。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]