[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910650":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910650,587,2,"多选题","在流水施工过程中，为使施工段划分得合理，一般应遵循下列原则（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","同一专业工作队在各个施工段上的劳动量应大致相等",true,{"key":16,"text":17,"correct":14},"B","每个施工段内要有足够的工作面",{"key":19,"text":20,"correct":14},"C","施工段的界限应尽可能与结构界限相吻合",{"key":22,"text":23,"correct":24},"D","对于多层建筑物、构筑物的工程，只能划分施工段，不能分施工层",false,{"key":26,"text":27,"correct":14},"E","施工段的数目要满足合理组织流水施工的要求","ABCE","2020版教材P109 本题考查的是流水施工的特点和参数。选项D的正确说法是，对于多层建筑物、构筑物或需要分层施工的工程，应既分施工段，又分施工层，各专业工作队依次完成第一施工层中各施工段任务后，再转入第二施工层的施工段上作业，依此类推。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]