[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910649":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910649,587,2,"多选题","组织流水施工时，确定流水步距应满足的基本要求是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","各专业队投入施工后尽可能保持连续作业",true,{"key":16,"text":17,"correct":14},"B","相邻专业队投入施工应最大限度地实现合理搭接",{"key":19,"text":20,"correct":21},"C","流水步距的数目应等于施工过程数",false,{"key":23,"text":24,"correct":21},"D","流水步距的值应等于流水节拍值中的最大值",{"key":26,"text":27,"correct":14},"E","各施工过程按各自流水速度施工，始终保持工艺先后顺序","ABE","2020版教材P111 本题考查的是流水施工的特点和参数。确定流水步距时，一般应满足以下基本要求：1）各施工过程按各自流水速度施工，始终保持工艺先后顺序；2）各施工过程的专业工作队投入施工后尽可能保持连续作业；3）相邻两个施工过程（或专业工作队）在满足连续施工的条件下，能最大限度地实现合理搭接。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]