[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910648":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910648,587,2,"多选题","下列关于无节奏流水施工，正确的说法是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","一般情况下流水步距不等",true,{"key":16,"text":17,"correct":14},"B","各施工段上的流水节拍不尽相等",{"key":19,"text":20,"correct":14},"C","专业工作队数等于施工过程数",{"key":22,"text":23,"correct":24},"D","一般用于结构简单、规模小的线型工程",false,{"key":26,"text":27,"correct":24},"E","各工作队连续施工，施工段没有空闲","ABC","2020版教材P115 本题考查的是流水施工的基本组织方式。非流水节奏施工的特点有：1）各施工过程在各施工段的流水节拍不全相等；2）相邻施工过程的流水步距不尽相等；3）专业工作队数等于施工过程数；4）各专业工作队能够在施工段上连续作业，但有的施工段之间可能有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]