[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910647":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910647,587,2,"多选题","建设工程组织加快的成倍节拍流水施工的特点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","同一施工过程的各施工段上的流水节拍成倍数关系",false,{"key":16,"text":17,"correct":18},"B","相邻施工过程的流水步距相等",true,{"key":20,"text":21,"correct":14},"C","专业工作队数等于施工过程数",{"key":23,"text":24,"correct":18},"D","各专业工作队在施工段上可连续作业",{"key":26,"text":27,"correct":14},"E","施工段之间可能有空闲时间","BD","2020版教材P114 成倍节拍流水施工的特点如下：1）同一施工过程在其各个施工段上的流水节拍均相等；不同施工过程的流水节拍不等，但其值为倍数关系；2）相邻施工过程的流水步距相等，且等于流水节拍的最大公约数（K）;3）专业工作队数大于施工过程数，即有的施工过程只成立一个专业工作队，而对于流水节拍大的施工过程，可按其倍数增加相应专业工作队数目；4）各个专业工作队在施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]