[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910646":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910646,587,2,"多选题","固定节拍流水施工的特点有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","各施工段上的流水节拍均相等",true,{"key":16,"text":17,"correct":14},"B","相邻施工过程的流水步距均相等",{"key":19,"text":20,"correct":14},"C","专业工作队数等于施工过程数",{"key":22,"text":23,"correct":24},"D","施工段之间可能有空闲时间",false,{"key":26,"text":27,"correct":24},"E","有的专业工作队不能连续作业","ABC","2020版教材P111 本题考查的是流水施工的基本组织方式。固定节拍流水施工是一种最理想的流水施工方式，其特点如下：①所有施工过程在各个施工段上的流水节拍均相等；②相邻施工过程的流水步距相等，且等于流水节拍；③专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工段上的任务；④各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]