[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910643":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910643,587,2,"多选题","在组织流水施工时，非节奏流水施工的特点包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","各施工过程在各施工段的流水节拍不全相等",true,{"key":16,"text":17,"correct":14},"B","相邻施工过程的流水步距不尽相等",{"key":19,"text":20,"correct":14},"C","专业工作队数等于施工过程数",{"key":22,"text":23,"correct":24},"D","专业工作队数大于施工过程数",false,{"key":26,"text":27,"correct":14},"E","各专业工作队能够在施工段上连续作业，但有的施工段之间可能有空闲时间","ABCE","2020版教材P115 按照流水节拍的特征，可将流水施工分为两大类：有节奏流水施工和非节奏流水施工。非节奏流水施工是指在组织流水施工时，全部或部分施工过程在各个施工段上的流水节拍不相等的流水施工。这种施工是流水施工中最常见的一种。非节奏流水施工的特点有：（1）各施工过程在各施工段的流水节拍不全相等；（2）相邻施工过程的流水步距不尽相等；（3）专业工作队数等于施工过程数；（4）各专业工作队能够在施工段上连续作业，但有的施工段之间可能有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]