[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910639":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910639,587,2,"多选题","下列建设工程项目目标控制方法中，可用来判断工程进度偏差的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","直方图法",false,{"key":16,"text":17,"correct":18},"B","网络计划法",true,{"key":20,"text":21,"correct":18},"C","S曲线法",{"key":23,"text":24,"correct":18},"D","香蕉曲线法",{"key":26,"text":27,"correct":14},"E","控制图法","BCD","2020版教材P102 可用来判断工程进度偏差的方法有网络计划法、S曲线法和香蕉曲线法。 直方图可掌握产品质量的波动情况，是静态分析方法；控制图也是分析产品质量的变化，是动态分析方法。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]