[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910637":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910637,587,2,"多选题","项目管理实施规划的主要内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目管理组织",false,{"key":16,"text":17,"correct":18},"B","质量计划",true,{"key":20,"text":21,"correct":18},"C","成本计划",{"key":23,"text":24,"correct":18},"D","设计与技术措施",{"key":26,"text":27,"correct":18},"E","进度计划","BCDE","2020版教材P88 本题考查的是工程项目计划体系。项目管理实施规划的主要内容包括：①项目概况；②总体工作安排；③组织方案；④设计与技术措施；⑤进度计划；⑥质量计划；⑦成本计划；⑧安全生产计划；⑨绿色建造与环境管理计划；⑩资源需求与采购计划；?风险管理计划；?信息管理计划；?沟通管理计划；?项目收尾计划；?现场平面布置；?技术经济指标。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]