[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910636":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910636,587,2,"多选题","在工程项目进度控制计划系统中，由建设单位负责编制的总进度计划表包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程项目进度平衡表",true,{"key":16,"text":17,"correct":18},"B","年度计划项目表",false,{"key":20,"text":21,"correct":14},"C","投资计划年度分配表",{"key":23,"text":24,"correct":18},"D","项目动用前准备工作计划表",{"key":26,"text":27,"correct":14},"E","工程项目总进度计划表","ACE","2020版教材P85 本题考查的是建设单位的计划体系。工程项目建设总进度计划的主要表格包括：工程项目一览表、工程项目总进度计划、投资计划年度分配表、工程项目进度平衡表。工程项目年度计划的表格部分包括：年度计划项目表、年度竣工投产交付使用计划表、年度建设资金平衡表和年度设备平衡表。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]