[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910633":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910633,587,2,"多选题","建设单位编制的工程项目年度计划包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","年度计划项目表",true,{"key":16,"text":17,"correct":18},"B","年度劳动生产率计划表",false,{"key":20,"text":21,"correct":18},"C","年度风险损失估算表",{"key":23,"text":24,"correct":14},"D","年度竣工投产交付使用计划表",{"key":26,"text":27,"correct":14},"E","年度建设资金平衡表","ADE","2020版教材P87 本题考查的是工程项目计划体系。工程项目年度计划是依据工程项目建设总进度计划和批准的设计文件进行编制的。工程项目年度计划主要包括文字和表格两部分内容。表格部分包括年度计划项目表、年度竣工投产交付使用计划表、年度建设资金平衡表和年度设备平衡表。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]