[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910632":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910632,587,2,"多选题","单位工程施工进度计划检查的主要内容包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第一个工人是否拥有足够的工作面",false,{"key":16,"text":17,"correct":18},"B","各工作项目的施工顺序、平行搭接和技术间歇是否合理",true,{"key":20,"text":21,"correct":18},"C","总工期是否满足合同规定",{"key":23,"text":24,"correct":18},"D","主要工种的工人是否能满足连续、均衡施工的要求",{"key":26,"text":27,"correct":18},"E","主要施工机具、材料等的利用是否均衡和充分","BCDE","2020版教材P96 当初始施工进度计划编制过后，需要对其进行检查与调整，以便使进度计划更加合理，进度计划检查的主要内容包括： (1)各工作项目的施工顺序、平行搭接和技术间歇是否合理； (2)总工期是否满足合同规定； (3)主要工种的工人是否能满足连续、均衡施工的要求 (4)主要施工机具、材料等的利用是否均衡和充分。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]