[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910628":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910628,587,2,"多选题","在建设单位的计划体系中，工程项目年度计划的编制依据包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程项目总进度计划",true,{"key":16,"text":17,"correct":18},"B","年度竣工投产交付使用计划",false,{"key":20,"text":21,"correct":18},"C","年度劳动力需求计划",{"key":23,"text":24,"correct":14},"D","批准的设计方案",{"key":26,"text":27,"correct":18},"E","技术组织措施计划","AD","2020版教材P86 工程项目年度计划是依据工程项目建设总进度计划和批准的设计文件进行编制的",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]