[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910626":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910626,587,2,"多选题","下列属于项目管理实施规划内容的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目概况",true,{"key":16,"text":17,"correct":14},"B","组织方案",{"key":19,"text":20,"correct":14},"C","技术措施",{"key":22,"text":23,"correct":14},"D","成本计划",{"key":25,"text":26,"correct":27},"E","财务评价指标汇总表",false,"ABCD","详见2020版教材P88 本题考查的是工程项目计划体系。项目管理实施规划应包括下列内容：1）工程概况；2）项目总体工作计划；3）组织方案；4）设计与技术措施；5）进度计划；6）质量计划；7）成本计划8）安全生产计划；9）绿色建造与环境管理计划10）资源需求与采购计划11）信息管理计划12）沟通管理计划13）风险管理计划14）项目收尾计划15）项目现场平面布置图16）项目目标控制计划17）技术经济指标",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]