[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910617":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910617,587,2,"多选题","工程项目施工过程中，应及时修改、补充施工组织总设计的情形是指（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工方案的重大修订",false,{"key":16,"text":17,"correct":18},"B","工程设计有重大修改",true,{"key":20,"text":21,"correct":18},"C","有关法律法规废止",{"key":23,"text":24,"correct":18},"D","主要施工资源配置有重大调整",{"key":26,"text":27,"correct":18},"E","施工环境有重大改变","BCDE","2020版教材P90 工程项目施工过程中，发生下列情形之一时，应及时修改、补充施工组织总设计：1）工程设计有重大修改；2）有关法律法规、标准的实施、修订或废止；3）主要施工方法有重大调整；4）主要施工资源配置有重大调整；5）施工环境有重大改变。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]