[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910614":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910614,587,2,"多选题","下列关于施工方案审批的说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工方案应由项目技术负责人审批",true,{"key":16,"text":17,"correct":18},"B","重点分部（分项）或专项工程的施工方案由施工单位负责人审批",false,{"key":20,"text":21,"correct":14},"C","有总承包单位时，应由总承包单位项目技术负责人核准备案",{"key":23,"text":24,"correct":14},"D","专项工程的施工方案应由施工单位技术部门组织相关专家评审",{"key":26,"text":27,"correct":14},"E","规模较大的分部（分项）的施工方案应按单位工程施工组织设计进行编制和审批","ACDE","2020版教材P97 施工方案应由项目技术负责人审批，重点、难点分部（分项）或专项工程的施工方案应由施工单位技术部门组织相关专家评审，施工单位技术负责人批准。由专业承包单位施工的分部（分项）或专项工程的施工方案，应由专业承包单位技术负责人或其授权的技术人员审批；有总承包单位时，应由总承包单位项目技术负责人核准备案。规模较大的分部（分项）或专项工程的施工方案应按单位工程施工组织设计进行编制和审批。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]