[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910613":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910613,587,2,"多选题","施工方案施工安排中应包括的内容是指（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程施工目标",true,{"key":16,"text":17,"correct":18},"B","资源配置计划",false,{"key":20,"text":21,"correct":14},"C","工程施工顺序及施工流水段",{"key":23,"text":24,"correct":14},"D","工程施工的重点和难点分析",{"key":26,"text":27,"correct":18},"E","施工进度计划","ACD","2020版教材P97 施工安排中应包括下列内容：（1）工程施工内容。包括：进度、质量、成本、安全生产及环境保护等目标，各项目标应符合施工合同和总承包单位对工程施工的要求。（2）工程施工顺序及施工流水段。（3）工程施工的重点和难点分析，并简述主要的管理和技术措施。（4）根据分部（分项）或专项工程的规模、特点、复杂程序、目标控制和总承包单位的要求设置项目管理组织机构，明确岗位职责。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]