[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910610":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910610,587,2,"多选题","建设工程采用平行承包模式时，建设单位控制工程造价难度大的原因有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同价值小，建设单位选择承包单位的范围小",false,{"key":16,"text":17,"correct":14},"B","合同数量多，组织协调工作量大",{"key":19,"text":20,"correct":21},"C","总合同价不易在短期内确定，影响造价控制的实施",true,{"key":23,"text":24,"correct":14},"D","建设周期长，增加时间成本",{"key":26,"text":27,"correct":21},"E","工程招标任务量大，需控制多项合同价格","CE","2020版教材P78 本题考查的是工程项目发承包模式。平行承包模式的特点之一，工程造价控制难度大，一是由于总合同价不易短期确定，从而影响工程造价控制的实施；二是由于工程招标任务量大，需控制多项合同价格，从而增加工程造价控制的难度。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]