[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910600":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910600,587,2,"多选题","工程项目管理的核心任务是控制项目目标，项目目标有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","造价控制",true,{"key":16,"text":17,"correct":18},"B","合同控制",false,{"key":20,"text":21,"correct":14},"C","质量控制",{"key":23,"text":24,"correct":14},"D","进度控制",{"key":26,"text":27,"correct":18},"E","索赔控制","ACD","2020版教材P71 本题考查的是工程项目管理及其类型。工程项目管理的核心任务是控制项目基本目标（造价、质量、进度），同时兼顾安全、环保、节能等社会目标，最终实现项目功能以满足使用者需求。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]