[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910586":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910586,587,2,"多选题","根据《国务院关于投资体制改革的决定》，只需审批资金申请报告的政府投资项目是指采用（ ）方式的项目。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","直接投资",false,{"key":16,"text":17,"correct":14},"B","资本金注入",{"key":19,"text":20,"correct":21},"C","投资补助",true,{"key":23,"text":24,"correct":21},"D","转贷",{"key":26,"text":27,"correct":21},"E","贷款贴息","CDE","2020版教材P64 本题考查的是工程项目建设程序。对于采用投资补助、转贷和贷款贴息方式的政府投资项目，则只审批资金申请报告。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]