[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910515":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910515,587,2,"多选题","美国建筑师学会的合同条件采用的计价方式包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总价",true,{"key":16,"text":17,"correct":18},"B","单价",false,{"key":20,"text":21,"correct":14},"C","成本补偿",{"key":23,"text":24,"correct":14},"D","最高限定价格",{"key":26,"text":27,"correct":18},"E","利润补偿","ACD","本题考查的是发达国家和地区的工程造价管理。AIA合同条件主要有总价、成本补偿及最高限定价格等计价方式。2020教材P16-21",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]