[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910509":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910509,587,2,"多选题","AIA合同条件的计价方式包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总价",true,{"key":16,"text":17,"correct":18},"B","单价",false,{"key":20,"text":21,"correct":14},"C","成本补偿",{"key":23,"text":24,"correct":14},"D","最高限定价格",{"key":26,"text":27,"correct":18},"E","利润补偿","ACD","2020版教材P21 AIA合同条件主要有总价、成本补偿及最高限额价格等计价方式。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]